Road Works and Storm Water Drainage Network – Sabah Al Ahmad, Al Khiran, Kuwait
Earth Works; Earthworks, including excavation and embankment, contains: Road (6) (ST: 1+000 TO ST: 11+700); Cumulative Fill = 986,839.16 m3; Cumulative Cut
775 New York Ave, Brooklyn, NY 11203
Looking for a quality and affordable builder for your next project?
We are happy to meet you during our working hours. Please make an appointment.
Earth Works; Earthworks, including excavation and embankment, contains: Road (6) (ST: 1+000 TO ST: 11+700); Cumulative Fill = 986,839.16 m3; Cumulative Cut
Construction of wastewater collection and conveyance systems, the design and construction of wastewater treatment plant in El Khiyam plain including operation, maintenance
The work comprises construction of raw water intake, construction of raw water pumping station, construction of transmission main from raw water PS
Construction of the main water pipeline (Force main) of pre-stressed concrete cylinder pipes (PCCP) having pressure 16 bar, starts from TGN with
Construction, completion and maintenance of bulk earthworks, main roads, parallel utilities, landscaping, design and construction of a packaged 3,300 m3/per day sewerage
Renovation by installation, construction, testing, commissioning and maintenance of sanitary sewerage network, fresh water & brackish water network, telephone works and all
Emergency maintenance works of water network in South East areas in Kuwait.
Expansion of existing Water Treatment Jubail Desalination & Power Plant Phase 2 facilities is to connect with the existing 84″ GRP pipeline
Civil maintenance and miscellaneous works at the power and water stations at Shuwaikh, Shuaiba (South), Doha (East), Doha (West), Az-Zour and Sabiya.
Rehabilitation & extension of water supply systems, including construction of potable water treatment plant, reservoir, pumping station & lifting pipe line. The