Infrastructure, Roads & Highways Work – MAK-Mohammed Abdulmohsin Al-Kharafi & Sons https://malkharafi.com Building the elements of life. Mon, 08 Jul 2019 09:57:58 +0000 en hourly 1 https://wordpress.org/?v=6.4.3 https://2xmaa8.p3cdn1.secureserver.net/wp-content/uploads/2020/10/cropped-Favicom-32x32.jpg Infrastructure, Roads & Highways Work – MAK-Mohammed Abdulmohsin Al-Kharafi & Sons https://malkharafi.com 32 32 Al Qassim Firing Ranges Project, Saudi Arabia https://malkharafi.com/myproject/al-qassim-firing-ranges-project/ Mon, 15 Oct 2018 10:59:17 +0000 https://mak.nji.ylj.mybluehost.me/?post_type=constructify-project&p=535 The scope includes: Infrastructure works (60km x 7m Asphalt road, 155 Km security fence, 122 Km earth berm) and structure building (offices, dinning hall, Mosque, underground and elevated water tank, guard house and observation towers.)

]]>
Road Works and Storm Water Drainage Network – Sabah Al Ahmad, Al Khiran, Kuwait https://malkharafi.com/myproject/road-works-storm-water-drainage-network-sabah-al-ahmad-al-khiran/ Mon, 08 Oct 2018 11:33:26 +0000 https://mak.nji.ylj.mybluehost.me/?post_type=constructify-project&p=541 Earth Works;

Earthworks, including excavation and embankment, contains: Road (6) (ST: 1+000 TO ST: 11+700); Cumulative Fill = 986,839.16 m3; Cumulative Cut = 49,579.61 m3; Road (5) (ST: 1+000 TO ST: 19+780); Cumulative Fill = 1,118,908.30 m3; Cumulative Cut = 440,727.82 m3; Road (4) (ST: 1+250 TO ST: 23+350); Cumulative Fill = 1,823,727.22 m3; Cumulative Cut = 219,506.69 m3

Road Works;

Construction and maintenance of temporary traffic detours necessary for the construction of other works. Demolition of existing pavement. Construction of temporary fence. Roadway work of (51,408 m) including sub-base and base courses, asphalt works, metal works and any other requirements to complete work. Construction of dual (3-lanes and 4-lanes) expressways including parallel collector distributor roads 2 lanes.

Utilities Works;

Construction of culvert for KOC pipelines protection. Construction of a storm water drainage network, including pump stations, culverts, pipes, manholes and gullies. Protection, relocation and construction of water pipelines, sanitary sewers. Protection, relocation and construction of irrigation work including pipes, valves, fittings.

Electrical Works & Instrumentation;

Protection, relocation and construction of electricity network 11kv. Construction of the necessary civil works for the relocation/protection of 33kv electric cables, and coordination with responsible authorities for the required relocation. Electrical work including cables, road crossing ducts, UPVC LT ducts, earth bonding & grounding. Construction of the necessary civil works for the relocation/protection of telephone cables, interfering with the works, and coordination with responsible authorities for the required relocation. Telephone work including UPVC ducts/pipes, manholes, optical fiber cable and sub duct (3×32+2×25) mm. Street Lighting work including cable trays, lighting columns, overhead guide signs, control cabinets. Traffic control system including ATC ducts, Fiber optic cable, CCTV camera, Speed camera system, VMS system, accident detection system.

Finishing & Landscape;

Removal and planting of palms, and removal and disposal for trees and shrubs interfering with the works. Road works, including pavement, sidewalks, signing and marking and concrete barriers

Bridge works;

139 m bridge for Interchange (IC 8). 50 meter bridge for Interchange (IC 7). Concrete works for bridges including blinding, combined footing, piers, retaining wall, abutments, precast parapet. Installation of pot bearing for abutment and piers, pre-stressed strands and pre-stressed concrete deck slab.

]]>
Construction and Maintenance of Roads, Bridges, Drainage, Sewer and Services for the completion of First Ring Road – Dasman and Abdullah Al Ahmad Street (Package II), First Ring Road (MC00) and Khaled Ibn Al Waleed Street (MC03) and Sour Street (MC05), Kuwait https://malkharafi.com/myproject/construction-and-maintenance-of-roads-bridges-drainage-sewer-and-services-for-the-completion-of-first-ring-road-dasman-and-abdullah-al-ahmad-street-package-ii-first-ring-road-mc00-and-khaled/ Mon, 08 Oct 2018 11:24:23 +0000 https://mak.nji.ylj.mybluehost.me/?post_type=constructify-project&p=564 Construction of three  troughs and five  bridges, two  pedestrian bridges and many related works such as: Road works 3,800 M of at-grade road ways, 1,750 M of depressed road ways (RC trough), Other upgrade works related to associated local roads and junction, road marking, road signs, street lighting’s, traffic signaling and associated works).

Structure Works

2 No. RC Trough (1A & 1B & 2) with tensioned piles, 4 No. vehicular post-tensioned case-in-place Bridges over main trough; 1 no. elevated post-tensioned case in place bridge; 2 no. reinforced concrete retaining walls, pedestrian pre-tensioned Bridges.

Utilities Works

Storm box culvert for storm work and sanitary drainage, utility box culvert, relocation and diversion of existing services and utilities (Fresh & Brackish Water, HT/LT electrical and telephone network);

Al-Mattabah Mosque Works

Design and construction of Al-Mattabah mosque building in the new location which specified by Kuwait Municipality. Demolish the old mosque and to remove the historical items from the old mosque and fix int he new constructed mosque.

Major Quantities

Concrete works: 165,000 m3; Reinforcement: 17,000 tons; Asphalt works: 170,000 m2; Road works: 4,000 m2, Electrical cables 11 kv : 9,000 m; Electrical cables 132 kv: 8,000 m; Water Networks: 21,000 m; Micro-tunneling (sanitary): 1,200 m; Sanitary (open cut): 600 m; Telephone Ducting: 143,000 m; Earthworks (excavation and filling): 1,200,000 m3.

]]>
Construction of Safaga Qenah 60 KM Road – Ministry of Transport, Egypt https://malkharafi.com/myproject/construction-of-safaga-qenah-60-km-road-ministry-of-transport/ Mon, 08 Oct 2018 11:22:33 +0000 https://mak.nji.ylj.mybluehost.me/?post_type=constructify-project&p=567 Construction of 60.00 km road, Earthwork (fill, normal cut, rock cut) Sub-base, Base Course & Asphalt (Binder 6 cm + Wearing 5 cm), Single & Double Barrier 80&90 cm.

Major quantities

Regular excavation: 400,000 m3; Rock excavation: 110,000 m3, Fill: 3,541,000 m3; rock protection: 217,600 m2; base and sub-base: 587,730 M3; Asphalt: 109,725 m3; Concrete slabs: 2,200 m3.

]]>
Sohag – Qena Road, Egypt https://malkharafi.com/myproject/sohag-qena-road/ Mon, 08 Oct 2018 11:20:12 +0000 https://mak.nji.ylj.mybluehost.me/?post_type=constructify-project&p=573 All Road works including crossing culverts and piping passing roots, traffic signs, etc.

]]>
Construction of Roads in New Military Entity, Egypt https://malkharafi.com/myproject/construction-of-roads-in-new-military-entity/ Mon, 08 Oct 2018 11:18:47 +0000 https://mak.nji.ylj.mybluehost.me/?post_type=constructify-project&p=575 Construction of earthwork (fill, normal cut, rock cut) Sub-base, Base Course & Asphalt ( Binder 6 cm + Wearing 5 cm), Single & Double Barrier.

Major quantities

Regular excavation, Rock excavation, Fill Rock protection, Base and sub-base, Asphalt, Concrete slabs, etc.

]]>
Military Entity – Asphalt Works, Egypt https://malkharafi.com/myproject/military-entity-asphalt-works/ Mon, 08 Oct 2018 11:17:18 +0000 https://mak.nji.ylj.mybluehost.me/?post_type=constructify-project&p=584 Paving: MC, RC, Asphalt Layers

]]>
Future City Roads Works, Egypt https://malkharafi.com/myproject/future-city-roads-works/ Mon, 08 Oct 2018 11:15:12 +0000 https://mak.nji.ylj.mybluehost.me/?post_type=constructify-project&p=585 Rehabilitation of existing roads works including walkways, lighting, asphalts, etc.

]]>
El-Oubour City Tunnels Construction, Egypt https://malkharafi.com/myproject/el-oubour-city-tunnels-construction/ Mon, 08 Oct 2018 11:13:28 +0000 https://mak.nji.ylj.mybluehost.me/?post_type=constructify-project&p=586 Two concrete tunnels construction  & auxiliary roads works

]]>
New Cairo 90th South Road Construction, Egypt https://malkharafi.com/myproject/new-cairo-90th-south-road-construction/ Thu, 04 Oct 2018 11:29:00 +0000 https://mak.nji.ylj.mybluehost.me/?post_type=constructify-project&p=587 Road Works (cutting, backfilling, base layers, asphalt layers, etc.)

]]>