Construction of a link road connecting four (4) villages – total length (5.5 km), dual carriageway, 6 m wide; removal of existing concrete track road, improvement on the horizontal and vertical alignment, formation of new sub-grade with imported fill of about 22,000 m3, placement of base material (9,000 m3), laying of asphaltic concrete (35,000 m2), concrete drains (6,000 m), various box and pipe culverts, etc. This is a design, finance and built basis contract, the design was done by MAK Engineers to the satisfaction of the Client.
Value
$6,100,000Client
Ministry Of Physical Planning Infrastructural Development, Natural Resources & Environment Nevis Island AdministrationConsultant
Ministry Of Physical Planning Infrastructural Development, Natural Resources & Environment Nevis Island AdministrationLocation
NevisCompletion
2008