Construction and Maintenance of 1,475 houses, public buildings and infrastructure for sector N2 of Jaber Al Ahmed City Housing Project, the project is divided to the following: (1) Soil Improvement of weak soil 1,615,000 m2; (2) 1,475 houses; (3) 70 units of vertical houses; (4) – Public Buildings: (a) 3 Kindergartens, (b) 4 Primary Schools, (c) 2 Intermediate Schools, (d) 2 Secondary Schools, (e) 4 Shops Groups, (f) Neighbourhood facilities (Police Station-Supermarket-Government Building), (g) Major Mosque, (h) 6 Local Mosque, (i) Clinic Center, (j) 57 Substations;
(5) – Infrastructure Works: (a) Sanitary Sewer Networks, (b) Storm Networks, (c) Water Supply Networks, (d) Road Pavement & Road Signs, (e) External Electrical Works, (f) Telephone Works, Asphalt: 165,000 m3, Concrete: 511,230 m3.
Value
$694,530,200Client
Public Authority for Housing WelfareConsultant
Public Authority for Housing WelfareLocation
KuwaitCompletion Date
Dec 2015